1.? ?Find and turn a piece of cast iron to fit the existing thread in the lathe bed. Epoxy or loctite in place and drill and tap a new hole aligned with the rack.
DO NOT try this by filling the thread with epoxy or steel, either one is too different from the cast iron to give a well aligned result.
2.? ?Fill and hammer the hole in the rack shut with a similar material. Drill new hole to line up with thread in bed casting.
3.? ?Leave both holes as they are and drill and tap a new hole 10 mm to one side, into rack and bed. Tap as needed and screw snug.



On Thu, Jan 13, 2022 at 9:10 PM <thomasfkeefe@...> wrote:
My lathe had pretty poor mesh between the handwheel gear and the rack.
To address the problem I slid the rack about 1/2 inch to one side and moved the
rack down. Everything worked out pretty well. However, one hole is a bit too
high. I am thinking of a couple of ways to fix the problem.

1. Start over and drill/tap all of the holes again. Hoping not to do this, as its not
? ? clear I will succeed the second time.

2. Elongate the through hole in the rack so that the screw will go in without distorting the
? ? rack. The hole is off by about .030" and I believe there is probably enough metal
? ? above the hole in the rack to fit. I am not sure what the rack is made of. It seems like
? ? steel which I don't think is hardened. But I don't really like the idea of changing the?
? ? rack this way.

3. Fill the hole with JB Weld or some other sort of epoxy-like filler and then re-drill and?
? ? tap. I assume this wouldn't be as strong as drilling the holes in new locations (i.e., #1 above)
? ? but I don't think this will be a concern. I haven't tried moving holes this way before so I am
? ? not sure it will be easy to move the holes a small amount like this.

I would like to get some advice on what is the best way to correct this. Thanks.

Tom