All dredging of contaminated sediments for Construction Season 1 has been finished. Placement of clean material is ongoing in the last of the Sediment Management Areas (SMAs) dredged this season.?Construction is done in SMAs 2B, 3, 4, 8, and 11B.?
The construction schedule continues to follow the times of high tides.?The active work sites are in shallow waters near the shore, and higher tides are needed to float the equipment. This work includes the movement of barges.
The high tides during the week of February 17 occur in the early mornings. Some work this week will be done outside normal hours (7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 7 p.m. on Saturdays). The schedule will vary but work may start as early as 4 a.m.?
Please note that in-water construction activities are tide and weather-dependent. All schedules are subject to change. Thank you for your patience as we wrap up Season 1 work.
For questions or concerns, you can reach our team at info@... or 1-888-561-LDWG (1-888-561-5394). Visit for the most up-to-date information.??
|