¿ªÔÆÌåÓý

ctrl + shift + ? for shortcuts
© 2025 Groups.io

Lower Duwamish Waterway Construction during the weeks of February 17 and February 24, 2025


 



South Park Neighborhood Association (SPNA)
monthly meetings, ?2nd Tuesday 6-7:30:
Duwamish River Community Hub
8600 14th Ave S

mailing address:
8201 10th Ave. S.
Seattle, WA 98108


---------- Forwarded message ---------
From: LDWG <info@...>
Date: Fri, Feb 14, 2025 at 4:12?PM
Subject: Lower Duwamish Waterway Construction during the weeks of February 17 and February 24, 2025
To: <spnaseattle@...>


/ / /

Cleanup Construction Activities

All dredging of contaminated sediments for Construction Season 1 has been finished. Placement of clean material is ongoing in the last of the Sediment Management Areas (SMAs) dredged this season.?Construction is done in SMAs 2B, 3, 4, 8, and 11B.?


The construction schedule continues to follow the times of high tides.?The active work sites are in shallow waters near the shore, and higher tides are needed to float the equipment. This work includes the movement of barges.


The high tides during the week of February 17 occur in the early mornings. Some work this week will be done outside normal hours (7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 7 p.m. on Saturdays). The schedule will vary but work may start as early as 4 a.m.?


Please note that in-water construction activities are tide and weather-dependent. All schedules are subject to change. Thank you for your patience as we wrap up Season 1 work.


For questions or concerns, you can reach our team at info@... or 1-888-561-LDWG (1-888-561-5394). Visit for the most up-to-date information.??

Weekly Environmental and Community Report for the week of February 3

You may view the weekly report and other previous weekly reports by clicking the link below.??

What to expect during the week of February 17

Construction will occur on President¡¯s Day, Monday, February 17.?


The remaining cleanup activity is backfilling (placing clean material) in SMA 6. A replacement tribal fishing pile in this area will be installed as soon as possible after backfilling. ?

?

Minor finishing work will occur for the SMA 9 sheet pile wall. This will be short duration and may occur during night-time due to the need to conduct the work during low tide.

?

The final surveys of dredged and backfilled SMAs 2A and C1 will be evaluated for completeness. See the map of cleanup areas linked below. ?

What to expect during the week of February 24

During the week of February 24, backfilling will continue in SMA 6. To complete this last area, the work will continue through February 28. We anticipate the work schedule during this week could begin as early as 12 a.m.

Backfill is carefully placed beneath the water surface (Photo credit: Geosyntec, week of February 10, 2025).

Backfilling must be done during high tides and requires working before sunrise (Photo credit: Geosyntec, week of February 10, 2025).

Send us an email
?
?

Stay informed during cleanup construction!

?

?

C?p nh?t th?ng tin trong qu¨¢ tr¨¬nh thi c?ng ?? d?n d?p

?

Mant¨¦ngase informado durante toda la actividad de construcci¨®n para la limpieza

?

???????????????????????????????????????????????????????????

Give us a call at 1-888-561-5394

LDWG | info@... | Seattle, WA 98108 US

| |

Join [email protected] to automatically receive all group messages.